Which is not one of the features of Arun Hydro-Electric Project (HEP) for which Union Cabinet recently approved an investment proposal of SJVN Ltd? |
| A. | The total generation capacity of Arun HEP is 900 MW. |
| B. | It is a Run-of-River scheme. |
| C. | It envisages about 70 meter high concrete gravity dam |
| D. | It envisages underground Power House containing three generating units of 300 MW each on Left Bank. |
| Answer» E. | |