| 1. |
Verify Scope is the process of |
| A. | progressively elaborating and documenting the project work that produces the product of the project. |
| B. | subdividing the major product deliverables into smaller, more manageable components. |
| C. | obtaining formal acceptance of the project scope by the stakeholders. |
| D. | influencing the factors that create scope changes to ensure that changes are agreed upon, determining that a scope change has occurred and managing the changes when and if they occur. |
| Answer» D. influencing the factors that create scope changes to ensure that changes are agreed upon, determining that a scope change has occurred and managing the changes when and if they occur. | |