1.
THE_SPACING_BETWEEN_CONSTRUCTION_JOINTS_IN_RIGID_PAVEMENT_IS?$
A.
4.5 m
B.
5.0 m
C.
5.5 m
D.
6.0 m
Answer» C. 5.5 m