1.

The ratio of the efficiencies of A, B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

A. 99 days
B. 102 days
C. 96 days
D. 93 days
Answer» C. 96 days