The purpose of work-break-down structure in project planning is mainly to1) Facilitate and improve the decision-making on procurement of resources .2) Relate activities under particular trade specializations to help in organizing for project staff3) Co-ordinate regarding milestone events across trade specialization to improve the synergy between the trades |
| A. | 1 and only |
| B. | 1 and 3 only |
| C. | 2 and 3 only |
| D. | 1, 2 and 3 |
| Answer» E. | |