| 1. |
The probability of completing the project can be estimated based upon the ____ . |
| A. | Uniform distribution curve |
| B. | Normal distribution curve. |
| C. | U-shaped distribution curve |
| D. | None of the above |
| Answer» C. U-shaped distribution curve | |