MCQOPTIONS
Saved Bookmarks
| 1. |
The method of measurement of concrete work specifies cubic content shall be worked out to the nearest |
| A. | 0.1 m3 |
| B. | 0.01 m3 |
| C. | 0.001 m3 |
| D. | 1.0 m3 |
| Answer» C. 0.001 m3 | |