1.

The following details pertain to the crossing of a canal with a natural drain.Full supply level in canal = RL 213.5 mBed level of canal = RL 212 mHigh flood level in drain = RL 210 mConsidering the given details, which type of cross drainage work is best suited to the site?

A. Aqueduct
B. Super passage
C. Syphon aqueduct
D. Syphon
Answer» B. Super passage