The following data is available for the economic analysis of alternate proposals for the same project. Conduct an economic evaluation and determine which of the two should be chosen for execution?Total annual highway cost of existing highway = ₹ 1,16,940Total annual road user cost of existing highway = ₹ 13,82,870Total annual highway cost of proposal A = ₹ 2,65,422Total annual road user cost of proposal A = ₹ 10,22,465Total annual highway cost of proposal B = ₹ 3,30,300Total annual road user cost of proposal B = ₹ 10,53,224 |
A. | None |
B. | A and B |
C. | B |
D. | A |
Answer» E. | |