1.

The figure below shows the network for a particular project which consists of four activities.Activity Normal time (days) Crash time (days) 1-2322-3422-4543-475The minimum time required for the completion of the project is _________

A. 9 days
B. 13 days
C. 14 days
D. 19 days
Answer» B. 13 days