MCQOPTIONS
Saved Bookmarks
| 1. |
The figure below shows the network for a particular project which consists of four activities.Activity Normal time (days) Crash time (days) 1-2322-3422-4543-475The minimum time required for the completion of the project is _________ |
| A. | 9 days |
| B. | 13 days |
| C. | 14 days |
| D. | 19 days |
| Answer» B. 13 days | |