| 1. |
The direct and indirect costs estimated by a contractor for bidding a project is Rs. 160000 and Rs. 20000 respectively. If the markup applied is 10% of the bid price, the quoted price (in Rs.) of the contractor is |
| A. | 196000 |
| B. | 182000 |
| C. | 200000 |
| D. | 198000 |
| Answer» E. | |