The detention period in a septic tank is assumed%!..
1.
The detention period in a septic tank is assumed%!
A.
20 minutes
B.
25 minutes
C.
30 minutes
D.
40 minutes
Answer» D. 40 minutes
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
While estimating a reinforced cement structure, the omitted cover of concrete is assumed%!
The measurement is not made in square meters in case of%!
The expected out turn of half brick partition wall per mason per day is%!
The cross-sections for a highway is taken at%!
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is%!
The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is%!
The detention period in a septic tank is assumed%!
While preparing a detailed estimate%!
Anti-siphonage pipe is connected to%!
*$_The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is?
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply