1.

The design flood commonly adopted in India for spillways of major projects is the:

A. Standard Project Flood
B. Flood with a Return Period of 100 years
C. Probable Maximum Flood
D. Flood with a Return Period of 10,000 years
Answer» D. Flood with a Return Period of 10,000 years