The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ______ weeks.ActivityDuration (weeks)Precedence RelationshipA5A < B, C, DB7B < E, F, GC10C < ID6D < GE3E < HF9F < IG7G < IH4H < II2---- |
| A. | 17 |
| B. | 21 |
| C. | 23 |
| D. | 25 |
| Answer» D. 25 | |