Statement I): The change in the critical path requires rescheduling in a PERT network.Statement II): Some of the activities cannot be completed in time due to an unexpected breakdown of equipment or non-availability of raw materials |
| A. | Both Statements I) and Statement II) are individually true and Statement II) is the correct explanation of Statement I) |
| B. | Both Statements I) and Statement II) are individually true but Statement II) is not the correct explanation of Statement I) |
| C. | Statement I) is true but Statement II) is false |
| D. | Statement I) is false but Statement II) is true |
| Answer» C. Statement I) is true but Statement II) is false | |