Statement (I): Critical path(s) through a CPM network can be identified even without working out the backward pass computations by a competent user.Statement (II): Critical path is the progressive chain of activities from start to finish (not excluding between splitting and merging nodes) through the network where Total Float is absent throughout (including through dummy arrows, if appropriate).

A. Both Statement (I) an Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
C. Statement (I) is true but Statement (II) is false
D. Statement (I) is false but Statement (II) is true
Answer» C. Statement (I) is true but Statement (II) is false