| 1. |
Statement (I): A linked-bar chart is premised on a resource-based scheduled network, and so is unique to the relevant project.Statement (II): A squared scheduled network drawn after allocating activity durations, with consideration of floats that have been originally available, may yet have the inputs-scheduling pending. |
| A. | Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I) |
| B. | Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I) |
| C. | Statement (I) is true but Statement (II) is false |
| D. | Statement (I) is false but Statement (II) is true |
| Answer» E. | |