1.

Statement (I): A linked-bar chart is premised on a resource-based scheduled network, and so is unique to the relevant project.Statement (II): A squared scheduled network drawn after allocating activity durations, with consideration of floats that have been originally available, may yet have the inputs-scheduling pending.

A. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
C. Statement (I) is true but Statement (II) is false
D. Statement (I) is false but Statement (II) is true
Answer» E.


Discussion

No Comment Found