Smith and Ajit can complete a task in 12 days and 18 days, respectively. If they work together on the task for 4 days, then the fraction of the task that will be left is: |
| A. | \(4 \over 9\) |
| B. | \(1 \over 9\) |
| C. | \(2 \over 9\) |
| D. | \(5 \over 9\) |
| Answer» B. \(1 \over 9\) | |