| 1. |
Sequence the following in the capital budgeting processA. Cash flow estimationB. Identify discounting rateC. Project selection decisionD. Determination of NPVChoose the correct answer from the options given below: |
| A. | A, B, C and D |
| B. | A, B, D and C |
| C. | D, A, B and C |
| D. | B, A, D and C |
| Answer» C. D, A, B and C | |