| 1. |
Satyam and Shivam can do a work in 10 days and 15 days respectively. Both start the work together, after 4 days Satyam left the work. Shivam has to complete the remaining work. In how many days, does the total work get completed? |
| A. | 10 |
| B. | 6 |
| C. | 12 |
| D. | 9 |
| Answer» E. | |