Ravi can complete a task in 6 days and Mohan can complete the task in 9 days. In how many days can Ravi and Mohan together complete the same task? |
| A. | \(3\frac{3}{5}\) days |
| B. | 9 days |
| C. | 15 days |
| D. | \(3\frac{2}{5}\) days |
| Answer» B. 9 days | |