Ratul and Praful together can complete a task in 18 days. They start the task together, but Ratul had to leave 7 days before the work got over. As a result it took a total of 23 days to complete the task. How many days would it have taken Pratul to complete the work by himself? |
| A. | 63 |
| B. | 51 |
| C. | 72 |
| D. | 54 |
| Answer» B. 51 | |