MCQOPTIONS
Saved Bookmarks
1. |
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects |
A. | Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity |
B. | Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity |
C. | The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time |
D. | The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time |
Answer» E. | |