1.

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer» D. Shortest duration


Discussion

No Comment Found

Related MCQs