On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?

A. Parametric modeling
B. Analogous
C. Rule of thumb
D. Fixed Rate
Answer» C. Rule of thumb