1.

On a straight railway track, absolute levels at point on two rails are 100.550 m and 100.530 m and the absolute levels at point B 100 m apart are 100.585 m and 100.515 m respectively, the value of twist of rails per metre run, is

A. 0.4 mm
B. 0.5 mm
C. 0.7 mm
D. 0.8 mm
E. 1.0 mm
Answer» C. 0.7 mm