Items of ‘C’ type are identified for a project using ABC analysis. Which of the following statements are true for them?a. Even rough quantity estimate is sufficientb. Bulk ordering is preferredc. Ordering of EOQ basis is preferredd. Even junior level staff authorized to order

A. All of the above
B. a, b and d
C. Only c
D. None of the above
Answer» C. Only c