During project staffing, the primary role of line management is |
A. | Approving the selection of the project manager |
B. | Approving the selection of assistant project managers |
C. | Assigning functional resources based upon who is available |
D. | Assigning functional resources based upon availability and the skill set needed |
Answer» E. | |