1. |
A contractor agreed to build 30 temporary sheds in 90 days at a price of Rs. 10000/unit. Twenty days later, the contractor has finished 8 sheds with an actual total cost ofRs. 85000. What is the status of the project? |
A. | The project is time and cost overrun |
B. | The project is time overrun and cost under run |
C. | The project is time under run and cost overrun |
D. | The project is time and cost under run |
Answer» D. The project is time and cost under run | |