Productivity performance variance is equal to:

A. Actual Productivity/Planned Productivity
B. Planned Productivity/Actual Productivity
C. Planned productivity minus actual productivity
D. Actual productivity minus planned productivity
Answer» D. Actual productivity minus planned productivity