Productivity performance variance is equal to: |
A. | Actual Productivity/Planned Productivity |
B. | Planned Productivity/Actual Productivity |
C. | Planned productivity minus actual productivity |
D. | Actual productivity minus planned productivity |
Answer» D. Actual productivity minus planned productivity | |