In the Determine Budget processes the project schedule |
| A. | is not one of the inputs to these processes. |
| B. | is used to allocate the project budget to the various project activities. |
| C. | is used to assign costs to the time period when the costs will be incurred |
| D. | is used to determine the size of the contingency component of the budget after all scheduled costs are accounted for. |
| Answer» D. is used to determine the size of the contingency component of the budget after all scheduled costs are accounted for. | |