1.

In an excavation of 3,000 cubic meter of common earth for a canal project, 6 men can be effectively employed on the job. If an output of a man is taken as 100 cubic meter per day, the duration of excavation activity will be

A. 5 days
B. 6 days
C. 7 days
D. 8 days
Answer» B. 6 days