| 1. |
If the difference in costs is $32000 and the slope coefficient is 0.40, then difference in machine hours would be |
| A. | $80,000 |
| B. | $12,800 |
| C. | $70,000 |
| D. | $22,800 |
| Answer» B. $12,800 | |