1.

If the budgeted cost in indirect cost pool is $144500 and total quantity of cost allocation base is $165500, then the budgeted indirect cost rate will be

A. 67.30%
B. 87.31%
C. 55.50%
D. 45.50%
Answer» C. 55.50%