1. |
If in a software project the number of user input, user output, enquiries, files and external interfaces are (15, 50, 24, 12, 8) respectively, with complexity average weighing factor. The productivity if effort - 70 person-month is |
A. | 110.54 |
B. | 408.74 |
C. | 304.78 |
D. | 220.14 |
Answer» C. 304.78 | |