1.

If ‘D’ is the duration ‘ES’ and ‘EF’ are then earliest start and finish times, ‘LS’ and ‘LF’ are latest start and latest finish times, the following relationship holds good.

A. F = LF - EF
B. IS = LF + D
C. LF = LS - ES
D. EF = ES + D
Answer» E.