Delhi Government recently approved the fourth phase of the Delhi Metro. In this context, which one of the following features given below is incorrect?

A. It features six corridors with a total 72 new stations.
B. It is targeted to be completed by 2022.
C. The cost of this phase of project is Rs. 50000 crore
D. It measures 103-km-long, of which 67 km will be elevated and rest underground.
Answer» C. The cost of this phase of project is Rs. 50000 crore