MCQOPTIONS
Saved Bookmarks
| 1. |
Assuming that the phases in a project are concept, development, implementation and termination, which phase typically has the highest degree of uncertainty? |
| A. | Concept |
| B. | Development |
| C. | Implementation |
| D. | Termination |
| Answer» B. Development | |