An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize? |
| A. | Additional resources using the contingency fund |
| B. | Escalation approval to use contingency funding |
| C. | Team overtime to meet schedule |
| D. | Corrective action based on causes |
| Answer» E. | |