1.

A small project consists of 3 activates P, Q and R to be executed in that sequence. The relationship between Time Duration (in ‘Units’ of time – T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith:P Q R TCTCTC825063408400923573201037510225829512350112159275 For a total duration of 25 units of time, the least total direct cost for the complete project will be

A. 965 units
B. 950 units
C. 940 units
D. 925 units
Answer» E.