

MCQOPTIONS
Saved Bookmarks
1. |
A project has 6 activities (A to F) with respective activity durations 7, 5, 6, 6, 8, 4 days. The network has three paths A - B, C – D and E – F. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is |
A. | 1 |
B. | 2 |
C. | 3 |
D. | 6 |
Answer» D. 6 | |