A pre-timed four-phase signal has a critical lane flow rate for the first three phases as 200, 187 and 210 veh/hr with a saturation flow rate of 1800 veh/hr/lane for all phases. The lost time is given as 4 seconds for each phase. If the cycle length is 60 seconds, the effective green time (in seconds) of the fourth phase is ______________ |
A. | 15.74 |
B. | 15.84 |
C. | 15.64 |
D. | 15.94 |
Answer» B. 15.84 | |