1. |
A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ? |
A. | 3 days |
B. | 4 days |
C. | 5 days |
D. | 6 days |
Answer» B. 4 days | |