1.

A non-pipeline system takes 50ns to process a task. The same task can be processed in six-segment pipeline with a clockcycle of 10ns. Determine approximately the speedup ratio of the pipeline for 500 tasks.

A. 6
B. 4.95
C. 5.7
D. 5.5
Answer» C. 5.7