A company has proposed to design a weir across a river in alluvial soil. The piezometric head at the bottom of the datum is computed as 10 m. The datum is 3 m below the floor bottom. The assured standing water depth above the floor is 2 m. The specific gravity of the floor material is 2.5. The required minimum thickness of the floor is: |
A. | 4.2 m |
B. | 2 m |
C. | 3.3 m |
D. | 1.5 m |
Answer» C. 3.3 m | |