A can do a piece of work in 80 days.He works at it for 10 days and then B alone finishes the remaining work in 42 days. The together could complete the work in how many days? |
| A. | 20 days |
| B. | 25 days |
| C. | 30 days |
| D. | 40 days |
| Answer» D. 40 days | |