1.

A can do a certain job in 12 days. B is 60% more efficient than A. The number of days, it takes B to do the same piece of work, is ?

A. 6
B. 7 * (1/2)
C. 6 * (1/4)
D. 8
Answer» C. 6 * (1/4)