A, B and C completed a work costing Rs. 1,800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A ? |
| A. | Rs. 800 |
| B. | Rs. 600 |
| C. | Rs. 900 |
| D. | Rs. 750 |
| Answer» D. Rs. 750 | |