1.

A and B can together finish a work in 30 days. They workd on it for 20 days, and then B left. The remaining work was done by A alone in 20 more days A alone can finish the work in

A. 60 days
B. 62 days
C. 58 days
D. 56 days
Answer» B. 62 days