| 1. |
A and B can do a work in 12 days , B and C in 15 days, C and A in 20 days. if A,B,C work together , they will complete the work in _____________ |
| A. | 10 DAYS |
| B. | 5 DAYS |
| C. | 47/3 DAYS |
| D. | 47/6 DAYS |
| Answer» B. 5 DAYS | |